Metro de Madrid will demand 1.2 million from OHL for the impact of the Canalejas Project on line 2

  • It also asks you to pay the cost of alternative buses
  • The affected section has been closed since the end of January

Metro de Madrid will require OHL an amount of 1.2 million euros and pay the alternative bus service that it has had to articulate to supply the closure of a section of line L2 due to the damage caused by the works of the Canalejas Project, the luxury residential, hotel and commercial project that the company is building in the city center.

A) Yes has been announced by the Minister of Transport of the Community of Madrid, Rosalía Gonzalo, on the eve of this section of line L2, the one between the Retiro and Sol stations, closed since last January 25 It will be put back into service tomorrow, Friday.

“When a problem arises in a public transport network and the origin is a company that is developing some works this has economic consequences, because it continues to be an impediment and a disorder for all the neighbors ”, explained Gonzalo.